Assignment Help, Cloud Based ERP System, Microsoft NAV Certification
WELCOME !!

Please Register, ask for assignment solutions & post the solutions if you know any.

LETS START POSTING YOUR IDEAS AND THOUGHTS AND BUILD THE COMMUNITY OF EXPERTS.

Assignment Help, Cloud Based ERP System, Microsoft NAV Certification
WELCOME !!

Please Register, ask for assignment solutions & post the solutions if you know any.

LETS START POSTING YOUR IDEAS AND THOUGHTS AND BUILD THE COMMUNITY OF EXPERTS.

Assignment Help, Cloud Based ERP System, Microsoft NAV Certification

Stock Market, Online Tutoring, Cloud Based ERP System, Microsoft Dynamics Reporting, Microsoft Nav Certification


You are not connected. Please login or register

View previous topic View next topic Go down  Message [Page 1 of 1]

1Rasuwagadhi Hydropower Present Status Empty Rasuwagadhi Hydropower Present Status 17th June 2015, 5:12 pm

Formatted

Formatted
Administrator
Rasuwagadhi Hydropower Present Status


PRESENT STATUS OF THE PROJECT
� PPA has been signed with NEA on November 14, 2011.
� Debt. Portion of the project will be fully financed by EPF for which the tri-partite loan agreement has been signed on 8 December, 2011 between RGHPCL, CHPCL and EPF.
� Selection of the Consultant has been made and contract has been signed on 3rd December, 2012.
� Pre-qualification for the civil and hydro-mechanical works in EPC model to construct RGHEP has been completed and Bid document has been issued to the pre-qualified bidders.
� Surface geological investigation, ERT works including drilling in headrace tunnel and tailrace tunnel has been carried out to determine the geological condition in the key structure locations.
� Generation license has been obtained from DoED on Dec 6, 2012.
� Certificate of Registration in Industry was obtained on July 3, 2012.
� Grid connection agreement with NEA has been completed.
� The Environmental Impact Assessment (EIA) report has been approved from the Ministry of Environment.
� Detail survey of double circuit 132 kV transmission line has been completed and design is under process.
� Private land acquisition has been completed.
� 125m out of 260m test adit tunnel at powerhouse site has been constructed.
� Construction of 11 kV construction power line from Chilime hub to the project site has been completed.
� Contract for the construction of Camp Facilities has been awarded and construction works has been started.
� IEE for 10 km long Transmission Line is under progress.